Modulars Update

This week, our electricians are hard at work running electrical wiring to the buildings. The concrete contractors are preparing to pour sidewalks and pads for the access ramps. Once the flatwork is complete, the modular will be “skirted” and the access ramps will be installed.
 
Later this month Mimeo projectors and whiteboards will be mounted and furniture will be moved in.